New runway at RAF Brize Norton following replacement works by VolkerFitzpatrick

VolkerFitzpatrick delivers its largest-ever airfield operating surfaces project at RAF Brize Norton

VolkerFitzpatrick has reached a major milestone in the delivery of the RAF Brize Norton project, the largest airfield operating surfaces project ever undertaken by the business.

Aircraft returning to the new runway at RAF Brize Norton

Aircraft return to RAF Brize Norton’s new runway


Aircraft have returned to RAF Brize Norton following the replacement of the Station’s 3km runway in just 16 weeks, marking a significant achievement within the wider programme to overhaul critical airfield infrastructure at the Station. The first aircraft touched down on the new runway on Friday 13th November. 

RAF Brize Norton is the RAF’s primary logistical hub, supporting military operations around the world. Delivering works of this scale within a live military environment has required extensive planning, close collaboration and careful coordination to maintain operational capability while providing certainty around a highly demanding programme.

New runway at RAF Brize Norton following replacement works by VolkerFitzpatrick

The runway works were undertaken during a critical 16-week closure, known as the ‘bolthole’, which began in July 2026. During this period, aircraft operations were dispersed to alternative locations, enabling operations to continue while the runway was replaced. 

Ahead of the closure, VolkerFitzpatrick undertook an extensive programme of enabling works, which began in September 2025. Preparations included establishing a secure, self-contained compound with direct access to the Base and creating a dedicated pass and vetting office accredited to follow Base security protocols.

The team also commissioned and trialled two asphalt batching plants and two concrete batching plants, stockpiling the materials required for the closure period, while establishing welfare and facilities capable of supporting a workforce of up to 500 people.

Aircraft returning to the new runway at RAF Brize Norton

These preparations were designed to maximise resilience, reduce programme risk and provide the delivery certainty required for infrastructure of such strategic importance to UK defence operations.

During construction, the team also responded to heightened operational activity at the Base. Additional aircraft movements and dangerous goods handling required regular, at times near-hourly, coordination with the RAF to ensure construction activities could continue safely without impacting military operations.

Aerial view of the new 3km runway at RAF Brize Norton

Building a more resilient runway for RAF Brize Norton


Despite these challenges, the team maintained progress and high levels of productivity throughout the closure, supported by detailed planning, close supply chain integration and strong working relationships between VolkerFitzpatrick, the Defence Infrastructure Organisation (DIO), Air Infrastructure, the RAF and wider project partners.

The new runway has been constructed using Pavement Quality Concrete (PQC), selected to improve resilience to higher temperatures and the effects of climate change. The use of PQC is expected to more than double the runway’s service life compared with the materials previously used, helping to ensure the Base remains operational and fit for decades to come while delivering long-term value for money. 

“This milestone represents much more than the successful delivery of a new runway. It demonstrates the strength of our people, the quality of our leadership and our ability to deliver critical national infrastructure in some of the most demanding operational environments. The scale, complexity and strategic importance of RAF Brize Norton required clarity, collaboration and confidence at every level. Our team has shown all three, working closely with the DIO, RAF and our supply chain partners to maintain momentum and make the right decisions throughout a challenging programme. I am immensely proud of everyone involved. The return of aircraft to the runway is a powerful demonstration of what VolkerFitzpatrick can achieve when strong leadership, technical expertise and genuine partnership come together. The operational importance of RAF Brize Norton meant there was no room for uncertainty. From establishing batching facilities and stockpiling materials through to responding to changing military requirements, the team and supply chain have worked together to build resilience into the programme from the outset.

James Hindes Managing Director, VolkerFitzpatrick

Aerial view of the new 3km runway at RAF Brize Norton

Bob Noyes, DIO Principal Project Manager, said:

“After an incredibly busy 16 weeks, it is fantastic to see aircraft returning home to RAF Brize Norton and using the new runway. I am proud of the immense teamwork that has gone into delivering this major element of the programme in such a short period, supporting the Station’s vital role in military operations around the world."

The runway replacement is part of a wider programme that includes the refurbishment of taxiways and associated infrastructure, upgrades to airfield lighting systems and improvements to drainage and supporting infrastructure. Together, these works will strengthen the airfield’s long-term operational capability, safety and resilience. 

The full airfield refurbishment project at RAF Brize Norton is expected to be completed in late 2027.