Over a weekend’s work, the team was able to move the project along, while minimising disruption to residents and rail users. A critical step in delivering the project, the twenty-five hour all line isolation was meticulously planned to deliver several activities. With the sky-scraping cranes brought onto site, the team was able to lift and install the three remaining concourse roof beams, and five pre-assembled upper canopies.
As planned, the escalator for the slow southern platform was fully installed, whilst the northern escalator was lifted onto the platform in three sections. Following the weekend works, the escalator sections were installed with the use of machine skates and lifting equipment.
Other works progressed during the weekend included installing copers (edging to the platforms) on the fast platform, with two teams working over two shifts. The cladding on the western overbridge was also advanced and scaffolding was installed to the sides of the concourse.
Like many of the specialist activities on site, it required great planning, skill, and precision to safely coordinate these activities over the railway infrastructure, and within the tight timeframe. Additionally, the teams planned their works to make efficient use of the cranes on site (two 500t and one 200t), plus excavators and forklifts. The project’s progress was captured with drones, making it possible to track the on-site developments digitally using advanced software.