VolkerFitzpatrick completed the base build and Cat A fit out of a regional distribution warehouse, pre-let to H&M

  • Single stage D&B of 760,000 ft2 distribution warehouse
  • 20m to haunch
  • Over 3,000 tonnes steel frame
  • Three storey, 44,000 ft2 offices with dining area
  • Three bailing compactors for waste disposal
  • We carried out guided site tours for 70 pupils from two local schools followed by talks on careers in construction
  • We liaised closely with tenant H&M ensuring their follow-on works were closely coordinated with our base build
  • We sequenced all our works to ensure efficient racking installation by Schafer

Facts and figures

  • Client
    Gazeley UK and H&M
  • Project Value
    £59m
  • Programme
    37 weeks
  • Project categories
    Building
+